NASA will not patch a defective Orion spacecraft electronics device successfully finished for the Artemis 1 mission despite deciding that the overall system was sufficiently redundant. NASA reported in a December 17 announcement that it had agreed to be used as is among the 8 spacecraft amounts of data units (PDUs) on the Orion spacecraft to offer connectivity between the computers of the spacecraft as well as other components. In another one of the two communications cards within this PDU, one of the redundant channels does not run.

The issue was first mentioned by The Verge that stated reports by the main contractor Lockheed Martin advised that this could take a year to repair the PDU since it is situated in an adapter between both the crew module as well as the service module, which is unavailable that now the two parameters are connected. NASA confirmed the issue with the PDU on November 30, stating it just was “troubleshooting the situation.” The time estimate predicted that perhaps the crew module would be separated from the service module, that may be the PDU will be restored, and also that the two modules will be merged as well as tested again.  

An alternate option could conclude the improvements in just 4 months but would entail removing connector panels to access the PDU, which was not intended for the hardware. NASA did not disclose in-depth on the potential replacements in its announcement on the decision not to repair the PDU but said the possibility of destroying the spaceship during the PDU replacement outweighs the potential any data loss should include the device totally malfunction.

Engineers, the organization stated, “evaluated that the threat of collateral damage outweighs the potential the risk related to loss of redundancy on one leg in an extremely redundant device because of the temporary access to this specific box, the level of aggressiveness of the complete structures of spacecraft as well as other variables.” “NASA maintains quality and reliability power and data system’s safety, which has gone through hundreds of hours of power procedures and monitoring,” the agency continued, adding that the PDU in question was already “fully operational.”

Even before the announcement, the prospect of carrying out a comprehensive modification to the spaceship to replace the PDU was played down by NASA Agency officials. Ken Bowersox, who serves as a deputy associate administrator of the Human Exploration and Operations Mission Directorate of NASA, stated during a December 7 media conference on a scientific update scheduled for the Artemis 3 manned lunar program, “You’ll have the first update, as well as the first report will display all the worst-case implications.” “We can notice that this is something on the best-case side that we can deal with.”